Powering critical infrastructure beneath the Hudson
Delivering medium-voltage certainty for a high-visibility tunnel project.
A new Hudson River tunnel project demanded flawless electrical infrastructure on an unforgiving timeline. With only a single-line diagram at bid stage and no finalized specifications, Turtle stepped into a design-development role, coordinating across a multi-party joint venture to finalize 15kV and 38kV switchgear configurations while maintaining strict utility conformance.
Through early production slot management and disciplined manufacturer coordination during a period of extended industry lead times, the team delivered all switchgear ahead of schedule without expediting premiums or schedule penalties.
The result: a multi-million dollar program executed without disruption on one of the region’s most publicly sensitive infrastructure projects, reinforcing that on high-visibility work, predictability is performance.